The ranking of what buyers ask for has not changed since November: B300 first, B200 second, and Hopper a minority ask. What has changed is what a provider should do about it before the new year.
This is the December edition of the monthly demand snapshot for providers. It reports direction and ranking only, covers GPU demand and nothing else, and focuses on what to have ready for the first quarter of 2027, when committed buyers tend to place the requests that fill capacity for the year.
- The ranking is stable: B300, then B200, then H200, with RTX PRO 6000 and GB300 NVL72 close together behind
- Blackwell-class parts account for the clear majority of requests that name a GPU
- Published specialist pricing rose through the autumn, so demand is not following price downward
- Providers holding Blackwell capacity should have a full specification and a firm date ready now
- Hopper holders should decide which terms to place it on while demand for it is still steady
- Future-dated listings let providers match against requests before hardware arrives
The ranking
| Rank | GPU | Direction versus the November snapshot |
|---|---|---|
| 1 | B300 | Unchanged, most requested |
| 2 | B200 | Unchanged, clear second |
| 3 | H200 | Unchanged, leads Hopper |
| 4 (tied) | RTX PRO 6000, GB300 NVL72 | Unchanged, similar frequency |
| 6 | H100 | Unchanged, smaller and steady |
| Other | AMD MI300-series, Vera Rubin, flexible | Small, persistent |
The previous edition set out what each position means. The detail is in the November snapshot, and the price context is in the November benchmark. This post does not repeat them. It asks a different question: given a ranking that is not moving, what is the useful thing to do in the weeks before year end?
Why a stable ranking matters
A ranking that holds across months is more informative than one that jumps. It suggests buyers are not reacting to a single announcement or a short-lived price move, and that the preference for the newest generation reflects workloads rather than fashion. Memory-bound inference and large-batch serving both reward the 288GB of a B300.
It also coincides with pricing that has not discouraged demand. Median on-demand H100 pricing rose 15% year over year to $3.42 per GPU-hour in late September, and specialist providers raised published rates in October. Buyers are asking for current-generation capacity into a market where prices are drifting up rather than waiting for them to fall.
The first-quarter pattern
Committed buyers plan on annual cycles. Budgets reset in January, training programmes are scoped for the year and procurement teams clear backlogs at the start of a quarter. For a provider that means December is a preparation month, because requests arrive in volume once the new year begins, and a listing that is complete and current when they do has an advantage over one still being assembled.
Buyers are told quotes return in under 24 hours. A provider that can answer technical questions in writing the same day is the one that wins the first conversation, and a provider that has to find the answers loses it.
If you hold Blackwell capacity
Complete the specification now. Interconnect generation and topology, rack power density, cooling method, support hours, replacement policy and a firm availability date should all be written down, because requests for current-generation hardware are the most specific. The preparation work is covered in what buyers mean by InfiniBand-ready and what a GPU buyer will ask your facility.
Decide your term ladder before the first request arrives. Committed B300 and B200 capacity prices by term, and a provider quoting on the spot with no ladder tends to quote inconsistently. The method is in how to price your GPU capacity for committed buyers.
If you hold Hopper capacity
Demand is smaller but steady, and it comes from buyers with clear workloads. H200 leads the group on memory, and H100 is a deliberate choice for single-node inference, fine-tuning and stacks built around it. Because retention on older parts falls with age, there is a case for placing Hopper on longer terms earlier in its life, a trade-off set out in short-term versus long-term demand.
Do not read a lower ranking as an instruction to discount. Hopper pricing has held, and committed H100 SXM bands are $2.50 to $3.00 per GPU-hour this quarter. Price from your cost floor and let the ranking inform how much capacity you place where.
Rack-scale and mid-tier
GB300 NVL72 and RTX PRO 6000 draw different buyers at similar frequency. Rack-scale demand comes from buyers whose workloads are communication-heavy, a case worked through in B200 versus GB200 NVL72, and who will ask detailed questions about cooling and failure domains. Mid-tier demand comes from teams running mid-sized inference that want 96GB on one card at a modest rate.
For both, specificity wins. A provider listing rack-scale capacity should state power per rack and cooling method plainly, and one listing RTX PRO 6000 should say what models fit on a card and at what throughput, since buyers compare cost per token rather than cost per hour.
AMD, Vera Rubin and flexible requests
The small categories deserve attention precisely because supply for them is thin. A provider with MI300-series or newer AMD capacity faces a smaller pool of requests but far fewer competitors, and a request that names Vera Rubin is a buyer planning ahead who will commit early if a delivery date is credible. Future-dated listings let a provider with Rubin on order match against those requests before hardware arrives.
Flexible requests, which describe a workload without naming a GPU, are an opportunity to recommend. A provider who can say which configuration suits a given model and why is more useful to that buyer than one who only lists inventory.
A year-end checklist
Reconcile your inventory against every listing and withdraw anything committed elsewhere. Update availability dates, since a date that slipped over autumn is worse than an honest later one. Refresh your specification sheet with measured figures. Set the rate ladder for each GPU you hold. And decide how much capacity to keep flexible for short-term requests and how much to place on committed terms.
If you have not yet listed, one node is enough to start, and the application takes about three minutes. The walkthrough is in the provider form, explained.
What this snapshot does not show
It ranks GPUs only. It does not report region, term length or deal volume, and it reflects requests rather than closed deals. It should be read alongside supply signals such as lead times and pricing, and it is one input to a decision about what to list, not a forecast.
List your capacity and start getting quoted.
One node is enough to start. There is no cost to apply or list.
Apply as a providerFrequently asked questions
Which GPUs are buyers requesting most in December 2026?
B300 first, B200 second and H200 third, with RTX PRO 6000 and GB300 NVL72 close together behind. Blackwell-class parts account for the clear majority of requests that name a GPU.
Has the ranking changed since November?
No. The order is unchanged, which suggests buyers are responding to workloads rather than short-term news.
What should providers do before January?
Complete specifications, set rate ladders, update availability dates, reconcile inventory across listings and decide how much capacity to place on committed terms.
Can I list capacity that arrives next year?
Yes. Capacity can be listed with a future available date and matched against requests that already exist.
Why does the snapshot not give numbers?
The useful signal for a provider is where demand concentrates, so it reports ranking and direction only and covers GPU demand alone.
Last reviewed: 10 November 2026. Demand direction drawn from buyer requests received through the GPUaaS.com network, reported as ranking only. On-demand median from the GetDeploying tracker via DataStorage, September 2026. Specialist rate changes from public pricing pages, October 2026. Committed bands from the GPUaaS.com October 2026 benchmark. Apply to list GPU capacity on GPUaaS.com.