Blog ▸ Power, Cooling and Rack Density: What a GPU Buyer Will Ask Your Facility

GPU Infrastructure

A buyer will ask about your power and cooling before your price. What an H100, B200 and B300 node draw, the density gap in older halls, cooling, PUE and how to answer in writing.

Power, Cooling and Rack Density: What a GPU Buyer Will Ask Your Facility

GPUaaS.com Team
GPUaaS.com Team
GPU Infrastructure
November 4, 2026
Blog post cover image
No items found.

A buyer will ask about your power and cooling before they ask about your price, because on current hardware the facility is part of the product.

A single Blackwell Ultra node draws about 14.5 kW, and many halls were designed for racks of 8 to 12 kW. This post covers the questions a buyer will put to your facility, the numbers behind them and how to answer in writing.

Key takeaways
  • An H100 or H200 node draws about 10 kW, a B200 node about 14 kW and a B300 node about 14.5 kW
  • Four nodes in a rack therefore need roughly 40 kW for Hopper and nearly 60 kW for Blackwell, and a GB300 NVL72 rack runs well above 100 kW
  • Halls built for 8 to 12 kW racks cannot take current-generation hardware without work
  • Liquid cooling is effectively required at Blackwell densities
  • Efficiency matters: at $0.10 per kWh a 14.5 kW node costs about $15,200 a year to power at PUE 1.2 and about $19,100 at 1.5
  • Write the answers down in a one-page facility sheet before the first quote

Why buyers ask about the facility

A GPU cluster that cannot be powered and cooled does not run, and one that throttles under heat runs slowly without anyone noticing. Buyers have been burned by capacity that was available on paper and constrained in practice, so they probe the physical layer early. A provider who answers cleanly is signalling that the hardware will perform as specified.

The questions also screen providers. A seller who cannot state rack density, cooling method and contracted power headroom is telling the buyer something, and the buyer will move on to one who can. Speed matters here too, because buyers are told quotes return in under 24 hours.

What the hardware draws

SystemApproximate draw per nodeFour nodes in one rack
HGX H100 or H200, eight GPUsAbout 10 kWAbout 41 kW
HGX B200, eight GPUsAbout 14 kWAbout 57 kW
HGX B300, eight GPUsAbout 14.5 kWAbout 58 kW
GB300 NVL72 rackRack-scaleWell above 100 kW per rack

Per-GPU draw has climbed from about 700 watts on an H100 to about 1,000 on a B200 and roughly 1,400 on a B300. Every generation makes the facility question harder.

The density gap

Many existing halls were designed for racks of 8 to 12 kW, which suited enterprise servers and storage. Against the figures above, a single H100 node nearly fills such a rack on its own, and one B300 node exceeds it. A hall like that can host Hopper at one node per rack, which strands floor space, or it needs electrical and cooling upgrades to host more.

Buyers will ask what each rack in the offered capacity is actually rated for, and whether the full cluster can run at that rating simultaneously, not just in a single rack. A hall with six racks at 40 kW but a feeder that supports only 150 kW in total cannot run them all together, and the answer has to be in the quote.

Cooling

Air cooling runs out of headroom somewhere in the 20 to 40 kW per rack range, depending on containment and airflow design. Rear-door heat exchangers extend that, and direct-to-chip liquid cooling carries the heaviest loads. At Blackwell densities liquid cooling is effectively required, and a GB300 NVL72 rack is designed around it.

State the method precisely: air with containment, rear-door exchangers or direct liquid cooling, and the coolant distribution arrangement. State the facility water or heat-rejection approach, which matters especially in hot climates. And state what happens during a cooling fault, since throttling under heat quietly reduces the throughput a buyer is paying for.

The power contract and redundancy

Buyers distinguish connected power from contracted power from available headroom. They want the contracted capacity for the hall, how much is already committed, and how much is free for this cluster. Contracted power in colocation commonly runs from $130 to $380 per kW per month, which alone accounts for $23,000 to $66,000 a year for a 14.5 kW node.

Redundancy is the next question. Is the feed single or dual, is backup N+1 or 2N, and does the SLA assume a particular level? Uptime commitments of 99.5% or better depend on this layer, and a provider who promises a number the power architecture cannot support is making a promise it will break.

Efficiency

Power usage effectiveness describes how much facility power is needed per unit of IT power. A 14.5 kW node running flat out uses about 127,000 kWh a year. At $0.10 per kWh and a PUE of 1.2 that costs about $15,200. At a PUE of 1.5 it costs about $19,100, a difference of nearly $3,900 per node per year.

Across a fleet of 100 nodes that is close to $390,000 a year, which is a real part of the cost to hold a GPU-hour. It belongs in the pricing method in how to price your GPU capacity for committed buyers, and buyers who understand it read a good PUE as a sign of a well-run facility.

Growth and delivery

Committed buyers plan to scale. They will ask whether the hall can take more nodes next quarter, and what the lead time is on additional power or cooling. A facility that can host the first cluster but not the second is a risk to a buyer planning a roadmap.

Delivery dates should account for the physical layer. Lead times run 16 to 26 weeks on current Blackwell, and a rack that arrives before the cooling is commissioned does not generate revenue. Capacity can be listed ahead of delivery, which only works if the date reflects when the facility will actually be ready.

The facility sheet

Write one page that answers the questions in advance. Rated kilowatts per rack and per row. The cooling method and the heat-rejection arrangement. Contracted and available power. Feed and backup redundancy. Measured PUE. Expansion headroom and lead time. Support access, remote hands and replacement times.

Put a paragraph from it in the free-text box of the provider application. The form is walked through in the provider form, explained, and the fabric side is covered in what buyers mean by InfiniBand-ready.

Common mistakes

Quoting rack density without confirming the whole hall can run at it together. Promising an uptime SLA the power architecture cannot support. Describing cooling as liquid-ready when it is not yet commissioned. Using nameplate power rather than measured draw. And committing a delivery date before the electrical work has a firm schedule.

List your capacity and start getting quoted.

One node is enough to start. There is no cost to apply or list.

Apply as a provider

Frequently asked questions

How much power does a GPU node draw?

About 10 kW for an eight-GPU H100 or H200 node, about 14 kW for B200 and about 14.5 kW for B300. A GB300 NVL72 rack runs well above 100 kW.

Can an older data centre host Blackwell hardware?

Not without work if it was built for racks of 8 to 12 kW. One B300 node exceeds that, so the hall needs higher-density power and, in practice, liquid cooling.

Is liquid cooling required?

Effectively yes at Blackwell densities. Air cooling runs out of headroom around 20 to 40 kW per rack, and rack-scale systems such as GB300 NVL72 are designed around liquid cooling.

How much does PUE matter?

At $0.10 per kWh a 14.5 kW node costs about $15,200 a year to power at PUE 1.2 and about $19,100 at 1.5, a gap of nearly $3,900 per node per year.

What should a facility sheet include?

Rated kilowatts per rack and row, cooling method, contracted and available power, feed and backup redundancy, measured PUE, expansion headroom and lead time, and support and replacement times.

Last reviewed: 5 November 2026. Node power draw from NVIDIA's published system specifications and Haink's AI infrastructure cost guide, 2026. Contracted power costs from the same guide. Lead times from Presenc AI GPU supply research. Energy-cost arithmetic assumes $0.10 per kWh and continuous full load, and is illustrative. Apply to list GPU capacity on GPUaaS.com.

Share this article:LinkedInX / TwitterCopy link
No items found.
FIND THE BEST GPU DEAL

Get a wholesale GPU quote in a few hours

NVIDIA B200, H200, H100, A100, RTX Pro 6000 — N. America, EU, MEA, APAC. No buyer fees.

Related articles